5225 North Academy Boulevard

Colorado Springs, Colorado 80918

 

 

 

Manitou Avenue Revitalization Project

Bi-Weekly Meeting Notes

Nolte Project #CSB0101700

 

 

Meeting Date:           February 26, 2004

Purpose:                     Bi-Weekly Meeting

Location:                    City Council Chambers

 

Introductions:  Representatives from The City of Manitou Springs (City), Nolte Associates, Inc. (Nolte), and the Manitou Avenue Liaison Group (MALG) were in attendance.  (See Attached Attendance Sheet.)  The meeting was opened at 11:00 a.m. by Steve Behrens, Nolte Project Manager. 

 

1.         Project Administration & Coordination

a.         Attendance Sheet and Introductions:   The attendance sheet was passed around and everyone introduced themselves.

b.         Minutes of the February 12, 2004 Bi-Weekly Meeting:  The minutes were distributed.

2.         Work in Progress

a.         CDOT Coordination:

§         Members of the Nolte Project Team and Manitou Springs met with Bob Torres, Mark Andrews, and Paul Reinsma of CDOT at 9:00, February 12, 2004.  The topics discussed included reducing Manitou Avenue to 3 lanes, 20 mph speed limit, roundabouts, utilities, drainage, ROW issues, and the design/build process.  Nolte presented a preliminary layout for Manitou Avenue.  The CDOT staff favorably received the concept.  Roger Miller, Nolte, also presented CDOT
”white paper” entitled "Manitou Springs Main Street Plan,” which provided rational background for Nolte’s approach to the Avenue design.  

b.                  CSU Coordination

§         Cindy Lou Hyde, CSU, discussed streetlights and undergrounding the electric lines.  She presented preliminary drawings which provided details on the existing overhead system including poles, location of connections, and streetlights.  There will be sixteen feeder vaults, four 6’x12’ three-phase transformer vaults, and several J-boxes which will feed the secondary overhead.  The vaults will be located underground in the amenity zone of the sidewalks.  They will be set flush with the finished grade.  The 6’x12’ transformer vaults will have a man-hole cover and the 4’x7’ feeder vaults will have grey finished top lids.  Cindy Lou indicated that future underground expansion is possible.  The  J-boxes will feed the streetlights and service lines to the buildings.  J-boxes measure one foot by six inches.  

§         Cindy Lou stated that this process can be done in phases.  However, CSU is trying to work out a financial package that will allow them to do the entire Manitou Avenue downtown area in one phase because it is easier, more cost effective, and less disruptive to businesses.

§         Cindy Lou presented a preliminary layout of street lights.  There are 36 lights on the design using CSU’s new decorative historic design streetlights with 100 watt luminaries.  This design will provide a footcandle and a uniformity ratio of .75.  The lights are about 85 feet apart and 16 feet in height.  They can have a back guard on them so that very little light is reflected backward; the light radiates forward and downward.  Question was raised about the possibly of installing the type of historic lights proposed in the “Avenue Plan.”  Could CSU accommodate this type of light?  Cindy Lou responded that if Manitou wants to purchase special lights there would need to be further discussions with CSU.  Use of streetlights other than the standard CSU product would increase their cost.  The City would have to purchase and install them, CSU would only provide the electrical wiring for connection.  Cindy Lou was given a copy of the information available on the desired historic lights and will research them.  One of the new CSU historic lights will be installed in a couple weeks on the corner by Soda Springs Park.    The final layout for streetlights will be developed along with the final design of the street.

c.                   Design Survey/Base Mapping

§         The field work has been completed.

d.                  Drainage Analysis: 

§         Nolte has received the drainage report completed for the Manitou Springs lofts and shops from Chuck Englund.  The Nolte Project Team is looking at how the inlets can be shifted to improve the local drainage.  Steve Behrens said that this problem will be improved when the curbs and inlets are moved.  The City will apply to FIMS to get mapping that is updated and provides additional coverage.

3.                  Urban Design Overview

§                     Mike Hussey, Nolte, reported that taking of photographs is about two-thirds complete and all other note taking on signage is completed and on the base map.

4.                  Owner/Tenant Overview

§                     About half of the interviews have been completed.

5.                  Other Items – These items were tabled until the next Bi-Weekly meeting.

a.         Trash Receptacles

b.         Shoshone Spring Font Update

c.         Miscellaneous Items

6.         Upcoming Events

a.   The vault analysis has been started with our subcontractor Summit Engineering.

b.      Preliminary Shoshone Spring Plaza Design

§         Mike Hussey will present preliminary Shoshone Spring demonstration project designs at the next Bi-Weekly meeting.

c.   The next Bi-Weekly Meeting will be on Thursday, March 11, 2004 at 10:00 a.m. at Manitou Springs City Hall.