5225 North Academy Boulevard

Colorado Springs, Colorado 80918

 

 

PROGRESS MEETING No. 5

PREVIOUS MEETINGS ATTENDEES:

Dino Bakkar Nolte Associates
Mike Leslie City of Manitou Springs
Bill Weaver AA Construction
Ron Herron AA Construction
Jack Elder MSAC
Kitty Clemens EDC/BID
Bill Gatti Qwest
Chris Cotterman Qwest
Roger Miller Nolte Associates


COPIES: Each attendee, Document Central, Central File

RECORDER: Dino Bakkar

DATE: May 4, 2005

TIME COUNT: 45 days charged through Saturday 04-16-05 with 39 remaining working days. To date, we lost 5 construction days to weather conditions

SCHEDULE
Completed Construction Activity Update, Ron Herron
Upcoming activities and schedule, Ron Herron


UTILITIES
Qwest

1. Since our last construction meeting Qwest was successful in splicing their new underground lines and lowering their overhead lines. They were also able to remove the old poles prior to concrete sidewalk placement

Adelphia

1. Adelphia was also successful in rerouting their lines, and no longer needed their location on the old poles.


CSU

1. CSU was able to coordinate with Qwest and remove their lines and lights from the poles prior to pole removals.
2. CSU screw-in bases schedule and line extension timeline?

MISCELLANEOUS ITEMS
New sidewalk protection.
Railing at the lofts.
Chuck Englund Schedule for the Shoshone Plaza area
Springs concrete stamp should be rigid for future projects